Key Dates
Follow Timber Ridge Village’s Milestones
This timeline estimates key dates in the coming months. Dates below are subject to change.
2024
May
05/24
Business Agreements
- Purchase and sale agreements will be distributed to business reservations.
05/24
Individual Buyer Outreach
- Individuals are invited to begin purchasing units on a first-come, first-served basis, Please complete the Contact form on this webpage to begin the process. Upon completing this form, you will be contacted by the development team to select a unit and execute a Purchase and Sale Agreement.
June
06/24
First Business PSAs are sent
06/24
First Individual PSAs are sent
August
08/24
Asbestos Abatement starts
08/24
Building Demolition starts
September
09/24
Site Demo starts
October
10/24
Build A Excavation starts
10/24
Soil Nails start
10/24
Build A Foundation starts
November
11/24
Building B Excavation starts
December
12/24
Building B Foundation starts
2025
January
01/25
Building G Foundation starts
April
04/25
CDOT Work starts
04/25
Building F Foundation starts
04/25
Build A Set Modular Units starts
May
05/25
Building E Foundation start
June
06/25
Building B Set Modular Units starts
06/25
Building C Foundation starts
July
07/25
Building D Foundation starts
07/25
CDOT Work Completion
September
09/25
Building F Set Modular Units starts
October
10/25
Building E Set Modular Units starts
November
11/25
Building A Completion
11/25
Building G Set Modular Units starts
December
12/25
Building D Set Modular Units starts
2026
January
01/26
Building C Set Modular Units starts
February
02/26
Building F Completion
July
07/26
Asphalt
07/26
Building B Completion
August
08/26
Building G Completion
08/26
Building C Completion
September
09/26
Building D Completion
09/26
Building E Completion
09/26
Landscaping Completion
October
10/26
Final Inspections Complete