The design and entitlement plans have received final approval from the Town of Vail. Construction of the Timber Ridge Village Condominiums will begin in the summer of 2024 beginning with demolition of the existing buildings and excavation of the site and the construction of the podium level of parking will immediately follow.
Vertical construction of each building will commence upon completion of the individual building pad sites. The development will be completed in phases with the projected completion of each building as follows:
Building A
Vertical Construction Start: April 2025
Building Complete: November 2025
Building B
Vertical Construction Start: June 2025
Building Complete: December 2025
Building E
Vertical Construction Start: August 2025
Building Complete: March 2026
Building F
Vertical Construction Start: August 2025
Building Complete: March 2026
Building C
Vertical Construction Start: December 2025
Building Complete: June 2026
Building D
Vertical Construction Start: October 2025
Building Complete: June 2026
Building G
Vertical Construction Start: December 2025
Building Complete: June 2026